RAPIDS Maintainers Docs

RAPIDS projects use an established set of guidelines and procedures for all projects. These are available for the community to review and provide feedback on.

Intended audience

Developers

Project Leads

Operations

Release v25.08 Schedule

NOTE: Dates are subject to change at anytime. Completed release schedules are posted here.

Phase Start End Duration
Development (cuDF/RMM/rapids-cmake/raft/dask-cuda/KvikIO/ucx-py) Thu, May 15, 2025 Wed, Jul 16, 2025 40 days
Development (others) Thu, May 22, 2025 Wed, Jul 23, 2025 40 days
Burn Down (cuDF/RMM/rapids-cmake/raft/dask-cuda/KvikIO/ucx-py) Thu, Jul 17, 2025 Wed, Jul 23, 2025 5 days
Burn Down (others) Thu, Jul 24, 2025 Wed, Jul 30, 2025 5 days
Code Freeze/Testing (cuDF/RMM/rapids-cmake/raft/dask-cuda/KvikIO/ucx-py) 1 Thu, Jul 24, 2025 Tue, Aug 5, 2025 9 days
Code Freeze/Testing (others) Thu, Jul 31, 2025 Tue, Aug 5, 2025 4 days
Release Wed, Aug 6, 2025 Thu, Aug 7, 2025 2 days

PROPOSED Release v25.10 Schedule

Phase Start End Duration
Development (cuDF/RMM/rapids-cmake/raft/dask-cuda/KvikIO/ucx-py) Thu, Jul 17, 2025 Wed, Sep 17, 2025 42 days
Development (others) Thu, Jul 24, 2025 Wed, Sep 24, 2025 42 days
Burn Down (cuDF/RMM/rapids-cmake/raft/dask-cuda/KvikIO/ucx-py) Thu, Sep 18, 2025 Wed, Sep 24, 2025 5 days
Burn Down (others) Thu, Sep 25, 2025 Wed, Oct 1, 2025 5 days
Code Freeze/Testing (cuDF/RMM/rapids-cmake/raft/dask-cuda/KvikIO/ucx-py) 1 Thu, Sep 25, 2025 Tue, Oct 7, 2025 9 days
Code Freeze/Testing (others) Thu, Oct 2, 2025 Tue, Oct 7, 2025 4 days
Release Wed, Oct 8, 2025 Thu, Oct 9, 2025 2 days
  1. Cross-library dependencies are pinned during this time-frame. For example: Dask and Distributed.  2